School Block Interior Finishes

Nyeri 2023 8 weeksInstitutional
School Block Interior Finishes

The brief

Classroom and laboratory finishing package including partitions, tiling, joinery and chemical-resistant laboratory flooring.

Project timeline

  1. Week 1–2

    Partitions and ceilings.

  2. Week 3–5

    Laboratory flooring and joinery.

  3. Week 6–7

    Tiling and decoration.

  4. Week 8

    Snagging and handover before term start.