All projectsInterior Finishes

Complete Bathroom Renovation

Kilimani, Nairobi 2025 3 weeksResidential
Complete Bathroom Renovation — after
Complete Bathroom Renovation — before
BeforeAfter

The brief

Full renovation of an existing bathroom including waterproofing, wall and floor tiling, new sanitary fittings, paint finishes, lighting and accessories.

Project timeline

  1. Week 1 — Strip out

    Protection of adjacent areas, demolition, disposal and substrate repair.

  2. Week 1 — Services

    Plumbing and electrical first fix, floor falls formed to the drain.

  3. Week 2 — Waterproofing

    Two-coat flexible membrane with flood test before tiling.

  4. Week 2 — Tiling

    Large format wall and floor tiling with precision setting out.

  5. Week 3 — Fit out

    Sanitary ware, vanity joinery, mirror lighting and accessories.

  6. Week 3 — Handover

    Snagging, deep clean, client walkthrough and care guidance.