The brief
Heavy-duty deck coating and waterproofing for a three-level commercial car park, with crisp bay marking and skid-resistant ramps.
Project timeline
Week 1
Level-by-level closure plan and substrate repairs.
Week 2–3
Waterproof coating application to decks and ramps.
Week 4
Line marking, numbering and pillar branding.
Week 5
Lighting coordination, cleaning and handover.