The brief
Seamless, non-porous antibacterial epoxy flooring with coved skirting installed across wards and corridors while the facility remained operational.
Project timeline
Phase 1
Survey, moisture testing and phasing plan agreed with facilities team.
Phase 2
Night works to corridors with full containment and negative pressure.
Phase 3
Ward-by-ward installation and coving.
Phase 4
Zoning, signage integration and clinical sign-off.