The brief
Reception and lobby fit-out featuring bespoke joinery, aluminium glazed partitions, gypsum bulkhead ceilings and large-format stone tiling.
Project timeline
Week 1–2
Setting out, shop drawings and material approvals.
Week 3–5
Ceilings, partitions and MEP coordination.
Week 6–7
Tiling and joinery installation.
Week 8–9
Decoration, lighting commissioning and snagging.